Is there any OOTB way to Rollback the deployed code to Production provided by Pega

  • azharrkv
    There is no straight forward configuration/set-up in Pega to Rollback the deployed code. But it can be achieved in below ways,

    • Taking a database back-up before deployment and restoring the back-up if something fails.
    • setting up point-in-time recovery for the database and restore it back to the preferred time if something fails.
    • taking a snapshot/image of the server (clone) and revert back if something fails.
    • deleting the versions deployed manually by unlocking it (not recommended).
    • restricting the application to point the versions before deployment (not recommended).

    Note: If your application runs in Pega cloud, then you might need Pega support to do the database back-ups. Pega also has an automatic back-up everyday which can be confirmed with your platform owner.

azharrkv
There is no straight forward configuration/set-up in Pega to Rollback the deployed code. But it can be achieved in below ways,

  • Taking a database back-up before deployment and restoring the back-up if something fails.
  • setting up point-in-time recovery for the database and restore it back to the preferred time if something fails.
  • taking a snapshot/image of the server (clone) and revert back if something fails.
  • deleting the versions deployed manually by unlocking it (not recommended).
  • restricting the application to point the versions before deployment (not recommended).

Note: If your application runs in Pega cloud, then you might need Pega support to do the database back-ups. Pega also has an automatic back-up everyday which can be confirmed with your platform owner.